The most important projects of our hydraulic team:

2015: Dismantling of a Müller-Weingarten 2.500 tons press in Switzerland, transport & logistics to Hungary

2016-2017: Reassembly of the above mentioned press, after a hydraulic and electrical refurbish including a new Siemens control,

 For this project we acquired the certificate from TÜV-Rheinland InterCert Kft. 2016: hydraulic refurbish of 2 aluminum melting furnaces at INOTAL Zrt.

2018: Dismantling, transport & logistics of 4 pieces of aluminum die-casting cells at Gruber & Kaja near Linz (Austria) and reassembly in Hungary

2020-2022: Assembly of 4 completely new casting cells for FRECH at NIDEC GPM Hungary Zrt.

2022-2023: hydraulic and electrical refurbish & conversion of 2 Zeulenroda 250 tons hydraulic presses. We have also acquired the TÜV certificate for these two presses.

 